A BILL TO BE ENTITLED
|
|
|
AN ACT
|
|
|
relating to the authority of a county to regulate the construction |
|
|
of certain industrial and offensive land use facilities. |
|
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
|
SECTION 1. Chapter 240, Local Government Code, is amended |
|
|
by adding Subchapter F to read as follows: |
|
|
SUBCHAPTER F. REGULATION OF CERTAIN INDUSTRIAL AND OFFENSIVE LAND |
|
|
USE FACILITIES |
|
|
Sec. 240.101. DEFINITIONS. In this subchapter: |
|
|
(1) "Alternative energy facility" means: |
|
|
(A) a wind power facility as defined by Section |
|
|
301.0001, Utilities Code; |
|
|
(B) a solar power facility as defined by Section |
|
|
302.0001, Utilities Code; or |
|
|
(C) a battery storage facility. |
|
|
(2) "Industrial facility" includes: |
|
|
(A) an electric generation facility; |
|
|
(B) an alternative energy facility; |
|
|
(C) a manufacturing or production facility; |
|
|
(D) a distribution or logistics center; |
|
|
(E) a data center; |
|
|
(F) a water or wastewater treatment plant; and |
|
|
(G) another heavy industrial or large-scale |
|
|
commercial facility. |
|
|
(3) "Offensive land use facility" includes a concrete |
|
|
plant, concrete crushing facility, landfill, solid waste transfer |
|
|
station, or automotive wrecking and salvage yard. |
|
|
Sec. 240.102. PERMIT REQUIRED. Notwithstanding any other |
|
|
law, a person may not construct an industrial facility or offensive |
|
|
land use facility in the unincorporated area of a county unless the |
|
|
person obtains a permit from the commissioners court of the county. |
|
|
Sec. 240.103. PERMITTING PROCEDURE. (a) A commissioners |
|
|
court of a county shall by order establish a procedure to review and |
|
|
approve an application for a permit to construct an industrial |
|
|
facility or offensive land use facility. |
|
|
(b) A permitting procedure established under this section |
|
|
must require: |
|
|
(1) a permit be issued by order of the commissioners |
|
|
court; and |
|
|
(2) the commissioners court to hold at least two |
|
|
public hearings on the application for the permit not less than two |
|
|
weeks and not more than two months apart. |
|
|
Sec. 240.104. DETERMINATION OF INDUSTRIAL OR OFFENSIVE LAND |
|
|
USE FACILITY. A commissioners court by order may determine that a |
|
|
facility proposed to be constructed is: |
|
|
(1) an offensive land use facility; or |
|
|
(2) an industrial facility, if the commissioners court |
|
|
by order determines that the proposed facility: |
|
|
(A) will require substantial infrastructure or |
|
|
resources when operational; or |
|
|
(B) by its nature, scale, or type of operations |
|
|
constitutes a facility that would be suited for location in a |
|
|
municipal zoning district that allows industrial use, if the |
|
|
project were proposed to be located in an area subject to municipal |
|
|
zoning regulation. |
|
|
Sec. 240.105. ISSUANCE OF PERMIT. (a) In issuing a permit |
|
|
required by this subchapter, a commissioners court must consider: |
|
|
(1) the compatibility of the proposed facility that is |
|
|
the subject of the permit with existing land uses in the surrounding |
|
|
area; |
|
|
(2) the potential impact of the facility on: |
|
|
(A) public health and safety; |
|
|
(B) air, water, and soil quality; and |
|
|
(C) local infrastructure, including roads, |
|
|
utilities, and emergency services; |
|
|
(3) public comment and input from county residents and |
|
|
other stakeholders; and |
|
|
(4) other factors that the commissioners court |
|
|
determines are relevant to balancing the interest in development |
|
|
and the welfare of the community. |
|
|
(b) A permit issued under this section may include |
|
|
conditions and requirements that the commissioners court |
|
|
determines are necessary to mitigate potential negative effects of |
|
|
the proposed facility that is the subject of the permit, including a |
|
|
requirement that the applicant implement measures for: |
|
|
(1) the protection of public health and safety, |
|
|
including providing necessary training and equipment for emergency |
|
|
services; |
|
|
(2) the improvement or maintenance of local |
|
|
infrastructure; |
|
|
(3) the protection of air, water, and soil quality; |
|
|
and |
|
|
(4) noise reduction. |
|
|
Sec. 240.106. REVOCATION OR SUSPENSION OF PERMIT. A |
|
|
commissioners court may revoke or suspend a permit issued under |
|
|
this subchapter if the commissioners court by order finds that: |
|
|
(1) the permit holder has violated the terms of the |
|
|
permit; or |
|
|
(2) the permitted project causes undue harm to the |
|
|
surrounding area or community. |
|
|
Sec. 240.107. ENFORCEMENT. The commissioners court of a |
|
|
county may adopt orders to enforce this subchapter or an order |
|
|
adopted under this subchapter. |
|
|
SECTION 2. This Act takes effect September 1, 2027. |