By: Perez of El Paso H.B. No. 730
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the interconnection of large load customers and the
  recovery of costs of generation facilities serving large load
  customers by electric utilities operating outside of the ERCOT
  power region.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 36.053, Utilities Code, is amended by
  adding Subsections (e), (f), and (g) to read as follows:
         (e)  In this subsection and Subsections (f) and (g):
               (1)  "Dedicated large load generation facility" means a
  generation facility, or a portion of a generation facility, that an
  electric utility operating solely outside of the ERCOT power region
  constructs, acquires, or contracts for primarily to serve one large
  load customer.
               (2)  "Large load customer" means a retail customer
  whose total load at a single site exceeds, or is projected to
  exceed, 75 megawatts. The term includes an affiliate or successor
  in interest of the customer.
         (f)  Notwithstanding Section 39.410 or any other law, the
  commission may not find that a dedicated large load generation
  facility is used by and useful to the electric utility in providing
  service, and the utility may not include the original cost of the
  facility in invested capital or otherwise recover the cost of the
  facility from customers other than the large load customer, unless
  the commission, in a proceeding for which notice is provided to each
  affected customer class and that is concluded before the cost is
  included in rates, finds that:
               (1)  the facility provides a net benefit to the
  utility's customers other than the large load customer; and
               (2)  the costs of the facility are allocated among
  customer classes in accordance with cost-causation principles and
  in a manner that does not cause the rates of the residential or
  small commercial customer classes to exceed the rates those classes
  would pay if the facility had not been constructed, acquired, or
  contracted for.
         (g)  The commission may make the findings described by
  Subsection (f) in a proceeding under Chapter 37 for a certificate of
  convenience and necessity for the facility or in a separate
  proceeding. Subsection (f) applies regardless of whether the large
  load customer has agreed to pay all or part of the costs of the
  facility for a limited period.
         SECTION 2.  Section 37.056, Utilities Code, is amended by
  adding Subsection (j) to read as follows:
         (j)  The commission may not grant a certificate for a
  dedicated large load generation facility, as defined by Section
  36.053(e), unless the commission:
               (1)  makes the findings described by Section 36.053(f);
  or
               (2)  conditions the certificate on the electric
  utility's agreement that the costs of the facility will not be
  recovered from customers other than the large load customer unless
  the commission later makes those findings in a proceeding described
  by Section 36.053(f).
         SECTION 3.  Subchapter I, Chapter 39, Utilities Code, is
  amended by adding Section 39.411 to read as follows:
         Sec. 39.411.  INTERCONNECTION OF LARGE LOADS. (a) In this
  section, "large load customer" includes an entity requesting an
  interconnection that exceeds the demand threshold established
  under Subsection (c) and a successor in interest to such an entity.
         (b)  The commission by rule shall establish standards for
  interconnecting large load customers to an electric utility subject
  to this subchapter in a manner designed to support business
  development in this state while minimizing the potential for
  stranded infrastructure costs, protecting the utility's other
  customers from costs caused by large load customers, and
  maintaining system reliability.
         (c)  The standards apply only to a customer requesting a new
  or expanded interconnection where the total load at a single site
  would exceed 75 megawatts, unless the commission determines that a
  lower threshold is necessary to accomplish the purposes described
  by Subsection (b).
         (d)  The standards must:
               (1)  require each large load customer to disclose to
  the electric utility whether the customer is pursuing a
  substantially similar request for electric service in this state or
  another state the approval of which would result in the customer
  materially changing, delaying, or withdrawing the interconnection
  request;
               (2)  set a flat study fee of at least $100,000 to be
  paid to the electric utility for initial transmission and
  generation screening studies, with any unused portion credited
  toward the customer's financial obligations for interconnection at
  the same site;
               (3)  include a method for a large load customer to
  demonstrate site control for the proposed load location through an
  ownership interest, lease, or another legal interest acceptable to
  the commission;
               (4)  include uniform financial commitment requirements
  for the development of transmission and generation infrastructure
  needed to serve a large load customer, which may be satisfied by
  security provided on a dollar per megawatt basis as set by the
  commission, contribution in aid of construction, advance payment
  for significant equipment or services, or another form of financial
  commitment acceptable to the commission; and
               (5)  provide that security posted under Subdivision (4)
  is refunded, in whole or in part, after application to any
  outstanding amounts owed, as the customer meets load ramp
  milestones and sustains operations for a period prescribed by the
  commission, if the customer withdraws all or part of its request, or
  if capacity subject to the commitment is reallocated to other
  customers.
         (e)  Information a large load customer submits under
  Subsection (d)(1) that is competitively sensitive is confidential
  and not subject to disclosure under Chapter 552, Government Code,
  except to the commission.
         (f)  Section 39.410 does not limit the application of the
  standards adopted under this section to a request for
  interconnection made on or after the effective date of the rules
  adopted under this section.
         SECTION 4.  (a) Section 36.053, Utilities Code, as amended
  by this Act, applies to a proceeding to change rates that is
  initiated on or after the effective date of this Act.
         (b)  Section 37.056(j), Utilities Code, as added by this Act,
  applies only to an application for a certificate of convenience and
  necessity filed on or after the effective date of this Act.
         (c)  The Public Utility Commission of Texas shall adopt rules
  under Section 39.411, Utilities Code, as added by this Act, not
  later than June 1, 2028.
         SECTION 5.  This Act takes effect September 1, 2027.