A BILL TO BE ENTITLED
|
|
|
AN ACT
|
|
|
relating to county authority to regulate the development of certain |
|
|
large electricity users. |
|
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
|
SECTION 1 Chapter 231, Local Government Code, is amended |
|
|
by adding Subchapter N to read as follows: |
|
|
SUBCHAPTER N. COUNTY REGULATION OF LARGE-LOAD ELECTRICITY USERS |
|
|
Sec. 231.301. DEFINITIONS. In this subchapter: |
|
|
(1) "Large computational load facility" means a tract |
|
|
or one or more contiguous or noncontiguous tracts of land under |
|
|
common ownership or control that are developed or proposed for |
|
|
development for use by a large computational load. |
|
|
(2) "County large computational load zoning district" |
|
|
means a zoning district established under this subchapter. |
|
|
(3) "Large computational load" means a business that: |
|
|
(A) is primarily engaged in: |
|
|
(i) creating, executing, and delivering |
|
|
software applications and services; |
|
|
(ii) artificial intelligence training, |
|
|
deployment, and delivery; |
|
|
(iii) adding virtual currency transactions |
|
|
to a distributed ledger; or |
|
|
(iv) other computational activities at a |
|
|
data center; and |
|
|
(B) is a large load under Section 37.0561, |
|
|
Utilities Code; or |
|
|
(C) a substation, transmission or distribution |
|
|
facilities, or other electric infrastructure designed to serve the |
|
|
facility or project; and |
|
|
(D) in determining whether a facility or project |
|
|
meets the requirements of Paragraph (B), the county may aggregate |
|
|
related facilities, phases, contiguous or noncontiguous tracts, |
|
|
meters, or projects that are under common ownership or control or |
|
|
are developed, financed, constructed, or operated as part of a |
|
|
common plan. |
|
|
(4) "Project" includes the construction of a new large |
|
|
computational load or a material expansion, redevelopment, or |
|
|
change in the use of an existing facility. A material expansion is |
|
|
an increase in electricity demand of at least 10 megawatts. |
|
|
Sec. 231.302. APPLICABILITY. This subchapter applies only to |
|
|
the unincorporated area of a county. |
|
|
Sec. 231.303. AUTHORITY TO ESTABLISH LARGE COMPUTATIONAL |
|
|
LOAD ZONING DISTRICTS. (a) To protect the public health, safety, |
|
|
and welfare, promote the orderly development of the county, and |
|
|
ensure that county residents benefit from large computational load |
|
|
development, the commissioners court may establish one or more |
|
|
county large computational load zoning districts and regulate the |
|
|
location and development of large computational load and large |
|
|
computational load within a district consistent with this |
|
|
subchapter. |
|
|
(b) A district may include all or part of the unincorporated |
|
|
area of the county. The boundaries of the district must be |
|
|
described by metes and bounds or shown on a map adopted as part of |
|
|
the order establishing the district. |
|
|
(c) A zoning district or district boundary is not effective |
|
|
until adopted by the commissioners court after a public hearing. |
|
|
Before adopting a district or district boundary, the commissioners |
|
|
court shall provide public notice and hold a public hearing in |
|
|
accordance with procedures adopted by the court. |
|
|
(d) After the commissioners court provides notice of a |
|
|
hearing to establish or amend a county large computational load |
|
|
zoning district, a person may not begin construction or development |
|
|
of, or materially expand, redevelop, or materially change the use |
|
|
of, a county large computational load facility within the area |
|
|
described in the notice until the commissioners court: |
|
|
(1) adopts or rejects the proposed district or |
|
|
amendment; or |
|
|
(2) fails to take action on the proposed district or |
|
|
amendment before the 91st day after the date notice is provided. |
|
|
Sec. 231.304. ZONING REGULATIONS. (a) The commissioners |
|
|
court may adopt reasonable zoning regulations within a county large |
|
|
computational load zoning district governing county large |
|
|
computational load facilities and large computational load, |
|
|
including regulations addressing: |
|
|
(1) the location of a county large computational load |
|
|
facility; |
|
|
(2) minimum lot size and tract dimensions; |
|
|
(3) setbacks, buffers, landscaping, screening, and |
|
|
open-space requirements; |
|
|
(4) measures reasonably necessary to protect nearby |
|
|
residential, educational, medical, agricultural, or |
|
|
environmentally sensitive uses from incompatible development; |
|
|
(5) access roads, traffic mitigation, emergency |
|
|
access, and transportation impacts; |
|
|
(6) noise, vibration, exterior lighting, and other |
|
|
off-site impacts; |
|
|
(7) water supply, water conservation, cooling |
|
|
technology, wastewater service, stormwater management, drainage, |
|
|
floodplain management, and land subsidence risks, as applicable; |
|
|
(8) fire protection, emergency response, law |
|
|
enforcement, and other public safety considerations; |
|
|
(9) improvements, mitigation measures, capacity |
|
|
requirements, and service arrangements necessary to address |
|
|
project-related demands on county roads, bridges, drainage and |
|
|
flood-mitigation infrastructure, facilities, services, and county |
|
|
infrastructure capacity; |
|
|
(10) disclosure of information necessary for the |
|
|
county to evaluate impacts on public infrastructure, water |
|
|
resources, emergency services, public safety, and county finances, |
|
|
subject to Chapter 552, Government Code; |
|
|
(11) reasonable mitigation measures, road-use |
|
|
agreements, infrastructure agreements, and cost-sharing agreements |
|
|
reasonably related to project impacts and necessary to ensure that |
|
|
project-related county infrastructure, mitigation, remediation, |
|
|
and service costs are borne by the project rather than county |
|
|
taxpayers; |
|
|
(12) performance bonds, closure bonds, site- |
|
|
restoration commitments, and other financial assurances necessary |
|
|
to ensure compliance and address abandonment, prolonged |
|
|
inactivity, decommissioning, demolition, remediation, removal of |
|
|
equipment or hazardous materials, and final site restoration; and |
|
|
(13) any other reasonable land-use regulation |
|
|
directly related to the public health, safety, or welfare or the |
|
|
orderly development of the county. |
|
|
(b) A zoning regulation adopted under this section must be |
|
|
reasonably related to a documented or reasonably foreseeable impact |
|
|
of a large computational load and may not be arbitrary or unrelated |
|
|
to a purpose authorized by this subchapter. |
|
|
(c) The county may determine the amount, form, duration, |
|
|
issuer, renewal requirements, and conditions for release of a |
|
|
performance bond, closure bond, letter of credit, or other |
|
|
financial assurance. The amount must be reasonably related to the |
|
|
anticipated cost of compliance, mitigation, remediation, |
|
|
decommissioning, or site restoration. |
|
|
(d) A county may not adopt regulations that directly |
|
|
conflict with a regulation adopted by a state agency. |
|
|
Sec. 231.305. SPECIAL USE PERMIT. (a) The commissioners |
|
|
court may require a person to obtain a special use permit before |
|
|
developing, constructing, materially expanding, redeveloping, or |
|
|
materially changing a county large computational load facility |
|
|
within a county large computational load zoning district. |
|
|
(b) An application for a special use permit may require: |
|
|
(1) submission of site plans and engineering studies; |
|
|
(2) information regarding traffic, water supply, |
|
|
wastewater, drainage, floodplain, emergency service, public |
|
|
safety, and county infrastructure impact analyses; |
|
|
(3) information regarding anticipated electric |
|
|
demand, energization schedules, load growth, and electric |
|
|
infrastructure associated with the project; |
|
|
(4) identification of any proposed water source and |
|
|
information regarding the availability of an adequate long-term |
|
|
water supply; |
|
|
(5) supporting documentation prepared or certified by |
|
|
a professional engineer licensed in this state demonstrating that |
|
|
the proposed electric, water, wastewater, and other utility service |
|
|
and any required infrastructure improvements are reasonably |
|
|
capable of serving the projected demand of the project without |
|
|
impairing existing service; |
|
|
(6) documentation that the project has been submitted |
|
|
to any applicable review or interconnection process required by the |
|
|
Public Utility Commission of Texas or administered by the Electric |
|
|
Reliability Council of Texas or another entity with jurisdiction; |
|
|
(7) information reasonably necessary to identify and |
|
|
evaluate measures to mitigate documented adverse impacts within the |
|
|
county's authority under this subchapter. |
|
|
(c) Before acting on a special use permit, the commissioners |
|
|
court may provide public notice and may hold a public hearing in |
|
|
accordance with procedures adopted by the court. |
|
|
(d) The county may determine whether an application is |
|
|
complete and may require the applicant to submit additional |
|
|
information reasonably necessary to evaluate the application. A |
|
|
permit application is not considered filed until the county |
|
|
determines that the application is complete. |
|
|
(e) The commissioners court may approve, conditionally |
|
|
approve, or deny a special use permit based on compliance with this |
|
|
subchapter and zoning regulations adopted under this subchapter. |
|
|
The county may make the final decision and any conditions imposed on |
|
|
the permit available to the public in a manner prescribed by the |
|
|
commissioners court. |
|
|
(f) A permit may be denied if the applicant fails to |
|
|
demonstrate compliance with applicable zoning regulations or fails |
|
|
to adequately address a documented or reasonably foreseeable impact |
|
|
within the county's authority under this subchapter. |
|
|
(g) After notice and an opportunity to cure, the county may |
|
|
suspend or revoke a special use permit for a material violation of |
|
|
this subchapter, a zoning regulation, or a condition of the permit. |
|
|
(h) The county may issue a stop-work order if construction |
|
|
or development is occurring without a required permit or in |
|
|
material violation of a zoning regulation or permit condition. The |
|
|
order remains effective until the violation is corrected or the |
|
|
order is modified or withdrawn by the county or a court. |
|
|
(i) The commissioners court may impose reasonable |
|
|
application, inspection, administrative, and professional-review |
|
|
fees including the reasonable cost of qualified consultants |
|
|
retained by the county, in an amount not to exceed the county's |
|
|
actual costs of administering this subchapter and reviewing the |
|
|
application. |
|
|
(j) Information submitted under this section is subject to |
|
|
Chapter 552, Government Code. A county may not enter into an |
|
|
agreement requiring the county to withhold information from public |
|
|
disclosure except to the extent withholding is authorized by that |
|
|
chapter or other law. |
|
|
Sec. 231.306. ELECTRIC REGULATION; PROJECT INFORMATION. |
|
|
(a) This subchapter does not authorize a county to regulate: |
|
|
(l) electric rates or electric service; |
|
|
(1-a) water rates or water service; |
|
|
(2) generation permitting; |
|
|
(3) transmission or distribution facility siting or |
|
|
interconnection standards; and |
|
|
(4) the operations of the Public Utility Commission of |
|
|
Texas or the Electric Reliability Council of Texas; |
|
|
(b) In evaluating a project under this subchapter, a county |
|
|
may request and consider information regarding: |
|
|
(1) anticipated electric demand; |
|
|
(2) the timing and scale of load growth; |
|
|
(3) planned substations, transmission or distribution |
|
|
facilities, or other electric infrastructure associated with the |
|
|
project; |
|
|
(4) the status of the project in any applicable review |
|
|
or interconnection process required or administered by the Public |
|
|
Utility Commission of Texas or the Electric Reliability Council of |
|
|
Texas; and |
|
|
(5) measures proposed to reduce impacts on county |
|
|
infrastructure, emergency services, public safety, water supplies, |
|
|
and neighboring property. |
|
|
(c) Nothing in this section prohibits a county from |
|
|
requesting or considering information concerning electric demand, |
|
|
energization schedules, substations, transmission or distribution |
|
|
infrastructure, interconnection status, reliability impacts, or |
|
|
curtailment capability for the purpose of evaluating land use, |
|
|
roads, drainage, water, emergency services, public safety, |
|
|
neighboring property, or county financial impacts. |
|
|
Sec. 231.307. NONCONFORMING USES. (a) A county large |
|
|
computational load facility lawfully developed, or a large |
|
|
computational load lawfully operating before the effective date of |
|
|
a zoning regulation adopted under this subchapter may continue as a |
|
|
lawful nonconforming use. |
|
|
(b) Zoning regulations adopted under this subchapter apply |
|
|
to a material expansion, redevelopment, or change in use of a |
|
|
nonconforming county large computational load facility or large |
|
|
computational load. In evaluating an expansion, redevelopment, or |
|
|
change in use, the county may consider the cumulative impacts of the |
|
|
existing county large computational load facility or large |
|
|
computational load and the proposed activity. |
|
|
(c) A county large computational load facility or large |
|
|
computational load is not entitled to nonconforming-use status |
|
|
solely because land has been purchased, a project has been |
|
|
announced, utility service has been requested, or a preliminary |
|
|
application has been submitted. |
|
|
Sec. 231.308. ENFORCEMENT. (a) A county may bring an |
|
|
action for injunctive relief to prevent or restrain a violation of |
|
|
this subchapter, a zoning regulation adopted under this subchapter, |
|
|
or a special use permit issued under this subchapter. |
|
|
(b) A person who violates this subchapter, a zoning |
|
|
regulation adopted under this subchapter, or a special use permit |
|
|
issued under this subchapter is liable to the county for a civil |
|
|
penalty of not less than $500 or more than $10,000 for each |
|
|
violation for each day the violation continues. |
|
|
(c) The county attorney or district attorney may bring an |
|
|
action under this section in a district court in the county. |
|
|
(d) A county that prevails in an enforcement action under |
|
|
this section may recover reasonable attorney's fees, court costs, |
|
|
investigative costs, and expert-witness fees. |
|
|
Sec. 231.309. CONSTRUCTION OF SUBCHAPTER. (a) This |
|
|
subchapter shall be liberally construed to accomplish its purposes |
|
|
of protecting the public health, safety, and welfare; promoting the |
|
|
orderly development of each county; and protecting neighboring |
|
|
property and public infrastructure; |
|
|
(b) This subchapter may not be construed to authorize a |
|
|
county to regulate electric rates, electric service, wholesale |
|
|
electric markets, electric reliability standards, or a matter |
|
|
assigned by state or federal law to the Public Utility Commission of |
|
|
Texas, the Electric Reliability Council of Texas, or a federal |
|
|
agency. |
|
|
Sec. 231.310. COORDINATION WITH COUNTY SUBDIVISION |
|
|
REGULATION. (a) Notwithstanding Section 232.001(h), a county may |
|
|
require an applicant for a plat or replat of property located within |
|
|
a large computational load zoning district to submit information, |
|
|
analyses, studies, plans, agreements, and financial assurances |
|
|
authorized by this subchapter or regulations adopted under this |
|
|
subchapter. |
|
|
(b) Notwithstanding Section 232.0025, an application for a |
|
|
plat or replat of property located within a county large |
|
|
computational load zoning district is not considered complete, and |
|
|
the period within which the commissioners court or county authority |
|
|
must approve, conditionally approve, or disapprove the application |
|
|
does not begin, until: |
|
|
(1) the county determines that the application |
|
|
includes the information required under this subchapter, |
|
|
regulations adopted under this subchapter, and Chapter 232; and |
|
|
(2) any special use permit required for the |
|
|
development proposed in the application has been finally approved; |
|
|
(c) The denial of a special use permit required for |
|
|
development proposed in a plat or replat application constitutes |
|
|
grounds for disapproval of the plat or replat application. |
|
|
SECTION 2. This Act takes effect September 1, 2027. |